6-7-22-Construction Progress-Suwa Arana project of the Indira cancer Trust - Current ongoing Project

We recently made a payment towards Bill#8 of the project. As of today, we have made payments up to $500,735 of the total SLMANA West Goal of $800,000. Archio, the construction company has made significant progress in time lost, where it is currently at 30 days behind schedule from 49 days previously. This has been accomplished with increased staff/crews and working multiple shifts and extended hours. They stand to catch up entirely in the coming months as long as material supply is not further inhibited

Taken from the main road. As you can see the 5th floor pillars are being completed before the 6th floor slab is laid